World’s
Tallest Chenab Rail Bridge – a Marvel Challenge
The world’s
tallest rail bridge over Chenab River in Jammu & Kashmir’s Reasi
district being constructed by Konkan Railway Corporation Limited (KRCL), a
Central Public Sector Enterprise under the Ministry of Railways, is likely to
be ready by 2016. This
bridge will be on the Udhampur – Srinagar –
Baramulla Rail Link (USBRL) project which is a national project to provide rail
connectivity to the beautiful valley of Kashmir . Konkan Railway has taken up the
construction of part of USBRL project from Katra to Dharam in December
2002. Chenab Bridge , perhaps the most challenging
project, is to be built at the height of 359 metres (height of Qutab Minar is
72 metres and of EiffelTower is 324 metres). Chenab Bridge is
having the central span of 457 metres. When constructed this bridge will
quality for world record for being the tallest rail bridge from the river bed.
Currently the world’s tallest rail bridge is located over France ’s Tam River with
its tallest pillar rising 340 metres, with the actual height where the train
runs on the bridge being 300 metres. The design of bridge also takes care of
blast load, which is internationally an unique feature. The painting scheme for this bridge is
designed for 35 years of service life so that during service life of 120 years,
only 3 times repainting will have to be done.
For
construction of Arch portion of the bridge over the river, a novel method of
construction using the cable car is designed and under construction. This cable
car runs on 54mm cables laid across the river valley and connected through 127
metre high
pylons (towers) on either side of river. The consumption of structural
steel for this project is very huge. The construction of Chenab Bridge will
comprises of earthwork in excavation for construction of foundations, over
46,000cum of concreting, 3600 tonnes of reinforcement steel and 25,000 tonnes of structural
steel (an equivalent to volume of a 54 story building on a football ground size
plot). Fabrication of the steel structures involves very high degree of
precision and quality wielding using latest wielding technologies.
Construction
of Railway Bridge over river Chenab bridging steep banks
on Bakkal (Katra) and Kauri (Srinagar )
ends respectively, without causing any hindrance to the water flow is a
challenge. Approach roads measuring a total length of about 5 kilometres are
being constructed in very difficult terrain to reach to main span
foundations. To ensure
stability of the foundation cut profiles, the slopes have been suitably
designed and will be protected by means of rock bolting and shotcreting. From
Katra side, the railway line
comes out of 5.9 kilometre long tunnel and after moving over other bridges
comes to a station called Salai-A and after moving over Chenab bridge comes to
a halt station called
Salai-B. These two stations are meant to serve the local population of either
side of the river.
The bridge
is designed for 266 kmph of wind velocity and wind tunnel simulation test for
the same was conducted in Denmark .
However, trains will not be permitted to travel over the bridge when wind
velocity exceeds 90 kmph. Suitable
instrumentation like anemometers for measuring wind velocity,
accelerometers for
measuring ground acceleration in the event of an earthquake, temperature
monitor etc., will be installed at critical locations to generate alarm to the
adjacent stations in case of danger. Various geotechnical investigations are
carried out for this bridge like soil boring done along the alignment of the
bridge, plate load test and shear load test conducted inside drift (a tunnel
like cavity made for investigation) at foundation level of Arch.
The section
from Katra to Dharam being constructed by Konkan Railway is 70 kilometres in
length. It comprises of 59,457 kilometres (85%) of route in tunnels, 6.6
kilometres (9%) of route on bridges and balance 6% of route in cutting and
embankments. To make access to these sites, Konkan Railway has to make 166
kilometres of project roads including road tunnels and many temporary Bailey
bridges.
The work was
pended in July 2008 for review of alignment and after review works were
restarted in September 2009. At
present, Final Location Survey for 28 km is in progress taking into account
changed ruling gradient of 1 in 80. The
target for completion of project is December 2017. To expeditiously execute the project
Konkan Railway has set up Project Head Office at Jammu . Its project camps are located at
Reasi, Kauri, Dugga and Sangaldhan. KRCL
has mobilized a team of about 240 staff and engineers for taking this project
ahead. The construction
machinery, plant, equipments, materials, technicians, skilled and un-skilled
manpower is arranged by KRCL’s construction contractors. For design support, various National
and International agencies have been engaged. The construction of 166 km
of approach/feeder roads through this inaccessible terrain is a challenging job
to take up the railway construction works.
Konkan Railway
has the experience of construction of 740 km of Railway route length between
Roha to Thokur (near Mangalore). This
route has 91 tunnels aggregating to 85 km, with Karbude tunnel of 6.5 km which
is the longest transport tunnel in the country. Over Konkan Railway route 179 major
bridges aggregating to 19.8 km of bridge length have been constructed. The longest bridge is across Sharavati River which is more than 2 km long.
No comments:
Post a Comment